CLUBHOUSE DEVELOPMENT – RENASCENT UPDATES


Works Completed Last Week

Last week, we installed the stainless-steel balustrades on the lower ground floor to the Main Stairs and throughout the building. The additional block retaining wall footing to the Eastern cart parking was also poured.

 

On the ground floor, services fit-off and commissioning works continued to progress, and we also progressed the installation of joinery throughout. We formed, reinforced and poured (FRP) the Porte Cochere and the remaining eastern path. We commenced the installation of upholstery to joinery items, along with the installation of the external signage.

 

We completed the carpet installation to the Gaming Lounge & Sports Bar Lounge. We also completed the installation of timber wall lining and curtains for the function room and the curtain for the family room. The installation of glazing, framing and door operators was completed around the building as lining works progressed. We finished the installation of the platform lift to the Sunken Terrace and commenced the installation of tactile and stair nosings.


The Wentworth Orange Clubhouse Progress

Works Planned for This Week

This week, the additional block retaining wall to the Eastern cart parking will be completed on the lower ground floor. On the ground floor, services fit-off and commissioning works will continue progressing. We will FRP the remaining spoon drain along the driveway and kerb & gutter in the carpark.

 

We will commence asphalt civil works and installation before the main entrance. We will progress with the installation of joinery & lining works throughout. We will also complete the installation of tactile & stair nosings throughout the building and the installation of the glass balustrade to the Main Stairs. We will complete the installation of carpet for the Main Bar and Lounge and Corian for the Main Bar. We will commence the installation of gaming machines & bases and progress the installation of external signage.

The Wentworth Orange Clubhouse Progress